The Chhattisgarh forest department has registered a Preliminary Offence Report (POR) against a senior National Mineral Development Corporation (NMDC) official after a mining waste dump collapsed in Dantewada district on November 18, officials said on Friday. A preliminary assessment indicates damage to 25-30 hectares of forest land, and the department is assessing the ecological damage and could impose a penalty of up to ₹2.5 crore.

Principal chief conservator of forests Arun Pandey said a case had been registered against the NMDC general manager and that an investigation would follow. Dantewada divisional forest officer Ranganadha Ramakrishna said the debris spread across nearly three kilometres, and the department was counting trees in 100-square-metre plots on both sides of the debris at six to seven locations to determine how many were buried. He said the penalty could be around ₹2 crore if 25 hectares were found affected and up to ₹2.5 crore if the damage extended to 30 hectares, noting that dense forests have around 260 to 271 trees per hectare.

In a statement, NMDC said a portion of an old waste dump at Deposit-14 had collapsed due to natural geological activity, and claimed the origin of the incident was in a forest area outside its mining lease, around two kilometres west of the lease area. The company said waste material had spread around 200 to 250 metres, while soil and gravel debris travelled two to three kilometres, and cited a January 2026 study by the Central Institute of Mining and Fuel Research, Dhanbad, which it said had found the dump to be stable. Local residents, however, had estimated the debris spread over 8-10 km in length and 300-500 metres in width, although the extent of damage was yet to be assessed.

Ramakrishna said the department would also issue notices to NMDC in connection with the latest incident and a similar landslide in 2024, in which around four hectares of forest were damaged, a POR was registered and the company was fined ₹10 crore, including an assessment of revenue loss, which it had not paid so far despite several notices. NMDC said the 2024 incident occurred due to severe floods at Deposit 11C and that it had received a notice around three months ago, adding that it was ready to cooperate. The district administration has sought an investigation by IIT Bombay experts, who inspected the site on Wednesday, with a preliminary report expected in 10 to 15 days, Dantewada collector Devesh Kumar Dhruv said.