The National High Speed Rail Corporation Limited (NHSRCL) has energised the Overhead Equipment (OHE) system on the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad bullet train corridor, covering both Up and Down lines, on November 20 as scheduled. The agency said the step would pave the way for further testing along the corridor.

The corridor uses a 2x25 kV Overhead Traction System, and energisation will be carried out gradually across smaller sections to ensure safety and compliance with prescribed procedures. The electrification network will have 14 Traction Substations along the 508-km route, drawing power from the National Grid. The first such substation, at Bilimora in Gujarat's Navsari district, has completed installation work in its Control Panel, Changeover Switch, Transformer and Circuit Breaker buildings, and will receive electricity from GETCO's 220 kV Ambetha Grid Substation.

The elevated stretch between Surat and Bilimora includes bridges across four rivers and a steel bridge over National Highway 53, along with around 94,000 noise barriers, according to NHSRCL. The agency has urged people to stay away from overhead electrical installations and not to approach or touch the equipment or carry out unauthorised work near it.

The corridor has 12 planned stations: Mumbai, Thane, Virar, Boisar, Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad and Sabarmati. The government is aiming to launch the first phase around mid-2027, planned between Surat and Vapi in Gujarat.